Leaves on the Line

Haymarket

HYM Scotland route
CSV JSON

1,407 delay minutes

The biggest share (18%) of the delay picked up at Haymarket in the four weeks to 9 December 2023 came from faulty trains.

69% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track302%8% 1 a day, more than 1 of the other 4 years-
Signals, points and power24517%16% 9 a day, more than 2 of the other 4 years1
Weather and structures1098%7% 4 a day, the most in 5 years-
Autumn16512%7% 6 a day, more than 2 of the other 4 years-
External9<1%4% 0 a day, the least in 5 years-
Network management16412%17% 6 a day, more than 2 of the other 4 years2
The operators' causes
Train faults25718%16% 9 a day, more than 2 of the other 4 years6
Traincrew14410%11% 5 a day, more than 1 of the other 4 years5
Stations574%3% 2 a day, more than 2 of the other 4 years-
Operations564%5% 2 a day, the least in 5 years-
Operator, other17212%7% 6 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Q3NZ Pumps T150
MPRail / wheel interface, adhesion problems (including ice on the running rail)114
TGDriver103
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles78
I1Overhead line/third rail defect68
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions58
M8Technical failures above the Solebar53
M1Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC)42
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)40
MNBrake and brake systems faults; including wheel flats where no other cause had been identified39
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver11,067
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)7,143
M8Technical failures above the Solebar4,929
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure3,573
IBPoints failure (including no fault found)3,165
MDTechnical failures below the solebar3,070
MNBrake and brake systems faults; including wheel flats where no other cause had been identified3,019
M7Door and Door system faults2,997
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,664
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure2,531