Haymarket
1,407 delay minutes
The biggest share (18%) of the delay picked up at Haymarket in the four weeks to 9 December 2023 came from faulty trains.
69% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 30 | 2% | 8% | 1 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 245 | 17% | 16% | 9 a day, more than 2 of the other 4 years | 1 |
| Weather and structures | 109 | 8% | 7% | 4 a day, the most in 5 years | - |
| Autumn | 165 | 12% | 7% | 6 a day, more than 2 of the other 4 years | - |
| External | 9 | <1% | 4% | 0 a day, the least in 5 years | - |
| Network management | 164 | 12% | 17% | 6 a day, more than 2 of the other 4 years | 2 |
| The operators' causes | |||||
| Train faults | 257 | 18% | 16% | 9 a day, more than 2 of the other 4 years | 6 |
| Traincrew | 144 | 10% | 11% | 5 a day, more than 1 of the other 4 years | 5 |
| Stations | 57 | 4% | 3% | 2 a day, more than 2 of the other 4 years | - |
| Operations | 56 | 4% | 5% | 2 a day, the least in 5 years | - |
| Operator, other | 172 | 12% | 7% | 6 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 150 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 114 |
| TG | Driver | 103 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 78 |
| I1 | Overhead line/third rail defect | 68 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 58 |
| M8 | Technical failures above the Solebar | 53 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 42 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 40 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 39 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 11,067 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 7,143 |
| M8 | Technical failures above the Solebar | 4,929 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 3,573 |
| IB | Points failure (including no fault found) | 3,165 |
| MD | Technical failures below the solebar | 3,070 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 3,019 |
| M7 | Door and Door system faults | 2,997 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,664 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 2,531 |