Leaves on the Line

Inverurie

INR Scotland route
CSV JSON

364 delay minutes

The biggest share (48%) of the delay picked up at Inverurie in the four weeks to 9 December 2023 came from weather and structures.

80% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track267%8% 1 a day, more than 3 of the other 4 years2
Signals, points and power4011%16% 1 a day, more than 2 of the other 4 years3
Weather and structures17548%7% 6 a day, more than 2 of the other 4 years17
Autumn62%7% 0 a day, more than 2 of the other 4 years-
External41%4% 0 a day, more than 1 of the other 4 years-
Network management3911%17% 1 a day, the least in 5 years18
The operators' causes
Train faults4011%16% 1 a day, more than 3 of the other 4 years18
Traincrew113%11% 0 a day, the least in 5 years3
Stations123%3% 0 a day, the most in 5 years-
Operations62%5% 0 a day, more than 3 of the other 4 years-
Operator, other62%7% 0 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure98
IWNon severe weather - snow/ice/frost affecting infrastructure equipment excluding points37
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions33
IKTelecom equipment failure (including no fault found)24
MNBrake and brake systems faults; including wheel flats where no other cause had been identified20
IRBroken/cracked/twisted/buckled/flawed rail16
TGDriver11
JBReactionary Delay to 'P' coded TSRs10
JPFailure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards10
RBPassengers joining/alighting10
Since 2018
CodeWhat Network Rail loggedMinutes
ZUNo Cause Identified After investigation by both Parties1,947
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles1,056
TGDriver1,026
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions771
IKTelecom equipment failure (including no fault found)754
MDTechnical failures below the solebar657
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail622
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure503
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure443
M8Technical failures above the Solebar441