Leaves on the Line

Keith

KEH Scotland route
CSV JSON

486 delay minutes

The biggest share (31%) of the delay picked up at Keith in the four weeks to 9 December 2023 came from weather and structures.

49% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track5511%8% 2 a day, more than 3 of the other 4 years-
Signals, points and power9319%16% 3 a day, more than 2 of the other 4 years-
Weather and structures14931%7% 5 a day, more than 2 of the other 4 years-
Autumn184%7% 1 a day, more than 1 of the other 4 years-
External71%4% 0 a day, the least in 5 years-
Network management5511%17% 2 a day, the least in 5 years-
The operators' causes
Train faults398%16% 1 a day, more than 3 of the other 4 years-
Traincrew306%11% 1 a day, the least in 5 years-
Stations112%3% 0 a day, more than 1 of the other 4 years-
Operations122%5% 0 a day, the most in 5 years-
Operator, other184%7% 1 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions65
IRBroken/cracked/twisted/buckled/flawed rail55
ICTrack circuit failure (including no fault found)44
X9Points failure caused by severe snow or ice where heaters are fitted and working as designed40
ZUNo Cause Identified After investigation by both Parties40
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure37
TGDriver29
IKTelecom equipment failure (including no fault found)23
MPRail / wheel interface, adhesion problems (including ice on the running rail)18
Q3NZ Pumps T18
Since 2018
CodeWhat Network Rail loggedMinutes
ZUNo Cause Identified After investigation by both Parties8,242
TGDriver1,846
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions1,846
IRBroken/cracked/twisted/buckled/flawed rail1,206
MPRail / wheel interface, adhesion problems (including ice on the running rail)955
Q3NZ Pumps T923
MDTechnical failures below the solebar664
XOExternal trees, building or structures encroaching or falling onto network infrastructure (not weather or vandalism)660
Q1Takeback Pumps578
M8Technical failures above the Solebar568