London Kings Cross
5,403 delay minutes
The biggest share (26%) of the delay picked up at London Kings Cross in the four weeks to 9 December 2023 came from signal, points and power faults.
79% of these minutes were knock-on from something that happened elsewhere first. 75% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 300 | 6% | 8% | 11 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 1,430 | 26% | 16% | 51 a day, the most in 5 years | 22 |
| Weather and structures | 577 | 11% | 7% | 21 a day, the most in 5 years | 16 |
| Autumn | 81 | 1% | 7% | 3 a day, more than 3 of the other 4 years | - |
| External | 371 | 7% | 4% | 13 a day, more than 2 of the other 4 years | 3 |
| Network management | 939 | 17% | 17% | 34 a day, more than 3 of the other 4 years | 58 |
| The operators' causes | |||||
| Train faults | 660 | 12% | 16% | 24 a day, more than 2 of the other 4 years | 20 |
| Traincrew | 738 | 14% | 11% | 26 a day, the most in 5 years | 74 |
| Stations | 124 | 2% | 3% | 4 a day, more than 3 of the other 4 years | - |
| Operations | 29 | <1% | 5% | 1 a day, more than 1 of the other 4 years | - |
| Operator, other | 155 | 3% | 7% | 6 a day, more than 3 of the other 4 years | 2 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| I1 | Overhead line/third rail defect | 999 |
| TG | Driver | 442 |
| I8 | Animal Strike or Incursion within the control of Network Rail | 342 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 277 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 271 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 261 |
| XR | Cable vandalism or theft | 232 |
| TI | Traincrew rostering problem | 217 |
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 159 |
| J0 | Telecom equipment radio failure (GSM-R) | 134 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 27,327 |
| I1 | Overhead line/third rail defect | 15,328 |
| IB | Points failure (including no fault found) | 11,975 |
| TI | Traincrew rostering problem | 11,920 |
| M8 | Technical failures above the Solebar | 9,678 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 8,614 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 7,849 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 7,200 |
| MU | Depot operating problem | 7,114 |
| MD | Technical failures below the solebar | 7,085 |