290 delay minutes

The biggest share (49%) of the delay picked up at Kingussie in the four weeks to 9 December 2023 came from weather and structures.

42% of these minutes were knock-on from something that happened elsewhere first. 69% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track6422%8% 2 a day, the most in 5 years-
Signals, points and power--16% 0 a day, the least in 5 years-
Weather and structures14149%7% 5 a day, the most in 5 years-
Autumn3<1%7% 0 a day, the least in 5 years-
External31%4% 0 a day, more than 1 of the other 4 years-
Network management2910%17% 1 a day, more than 1 of the other 4 years1
The operators' causes
Train faults3512%16% 1 a day, more than 2 of the other 4 years-
Traincrew72%11% 0 a day, more than 1 of the other 4 years-
Stations62%3% 0 a day, more than 2 of the other 4 years-
Operations--5% 0 a day, the least in 5 years-
Operator, other3<1%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
JKFlooding not due to exceptional weather89
JSCondition of Track TSR outside the Timetable Planning Rules64
IWNon severe weather - snow/ice/frost affecting infrastructure equipment excluding points39
M7Door and Door system faults25
OCSignaller including mis-routing (not ERTM /ETCS related)9
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)8
QMTrain schedule/STP Process including erroneous simplifiers7
TGDriver7
MDTechnical failures below the solebar6
OKDelay caused by Operating staff oversight, issues or absence (excluding signallers and Control)6
Since 2018
CodeWhat Network Rail loggedMinutes
MDTechnical failures below the solebar1,119
ZUNo Cause Identified After investigation by both Parties1,067
MCDiesel Loco failure, defect, attention883
ICTrack circuit failure (including no fault found)741
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions732
JSCondition of Track TSR outside the Timetable Planning Rules662
TGDriver624
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure497
XNRoad or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes)489
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.478