Leaves on the Line

Largs

LAR Scotland route
CSV JSON

162 delay minutes

The biggest share (27%) of the delay picked up at Largs in the four weeks to 9 December 2023 came from autumn leaves.

77% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power96%16% 0 a day, more than 1 of the other 4 years-
Weather and structures--7% 0 a day, the least in 5 years-
Autumn4427%7% 2 a day, the most in 5 years-
External32%4% 0 a day, more than 2 of the other 4 years-
Network management2717%17% 1 a day, more than 3 of the other 4 years-
The operators' causes
Train faults--16% 0 a day, the least in 5 years2
Traincrew2616%11% 1 a day, the most in 5 years2
Stations--3% 0 a day, the least in 5 years-
Operations2415%5% 1 a day, the most in 5 years-
Operator, other2918%7% 1 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver26
Q3NZ Pumps T25
TATrain-crew/loco/stock/unit diagram issues24
MPRail / wheel interface, adhesion problems (including ice on the running rail)24
OEFailure to lay Sandite or operate Railhead Conditioning train as programmed19
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)14
OCSignaller including mis-routing (not ERTM /ETCS related)7
QMTrain schedule/STP Process including erroneous simplifiers6
ICTrack circuit failure (including no fault found)5
J0Telecom equipment radio failure (GSM-R)4
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver751
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)746
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure466
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions364
IBPoints failure (including no fault found)347
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure342
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)300
M8Technical failures above the Solebar270
MPRail / wheel interface, adhesion problems (including ice on the running rail)257
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail252