Laurencekirk
695 delay minutes
Most of the delay picked up at Laurencekirk in the four weeks to 9 December 2023 came from weather and structures.
13% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 7 | 1% | 8% | 0 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 39 | 6% | 16% | 1 a day, the least in 5 years | - |
| Weather and structures | 416 | 60% | 7% | 15 a day, the most in 5 years | - |
| Autumn | 3 | <1% | 7% | 0 a day, the least in 5 years | - |
| External | 17 | 2% | 4% | 1 a day, more than 3 of the other 4 years | - |
| Network management | 167 | 24% | 17% | 6 a day, the most in 5 years | 1 |
| The operators' causes | |||||
| Train faults | 6 | <1% | 16% | 0 a day, more than 1 of the other 4 years | - |
| Traincrew | 19 | 3% | 11% | 1 a day, the most in 5 years | - |
| Stations | 3 | <1% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | 9 | 1% | 5% | 0 a day, the most in 5 years | - |
| Operator, other | 9 | 1% | 7% | 0 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 360 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 149 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 44 |
| IA | Signal failure (including no fault found) | 24 |
| TG | Driver | 19 |
| XP | BRIDGE HIT | 17 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 12 |
| X9 | Points failure caused by severe snow or ice where heaters are fitted and working as designed | 12 |
| ZU | No Cause Identified After investigation by both Parties | 12 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 9 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 2,680 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,159 |
| ZU | No Cause Identified After investigation by both Parties | 1,041 |
| IA | Signal failure (including no fault found) | 942 |
| OL | Signal Box not open during booked hours | 921 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 827 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 789 |
| TG | Driver | 541 |
| MD | Technical failures below the solebar | 522 |
| M8 | Technical failures above the Solebar | 480 |