Letchworth Garden City
1,283 delay minutes
The biggest share (41%) of the delay picked up at Letchworth Garden City in the four weeks to 9 December 2023 came from how the network was run.
68% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 29 | 2% | 8% | 1 a day, the least in 5 years | - |
| Signals, points and power | 127 | 10% | 16% | 5 a day, more than 3 of the other 4 years | 1 |
| Weather and structures | 27 | 2% | 7% | 1 a day, more than 3 of the other 4 years | - |
| Autumn | 64 | 5% | 7% | 2 a day, more than 3 of the other 4 years | - |
| External | 55 | 4% | 4% | 2 a day, more than 2 of the other 4 years | - |
| Network management | 524 | 41% | 17% | 19 a day, the most in 5 years | 23 |
| The operators' causes | |||||
| Train faults | 95 | 7% | 16% | 3 a day, more than 2 of the other 4 years | 8 |
| Traincrew | 250 | 19% | 11% | 9 a day, the most in 5 years | 5 |
| Stations | 6 | <1% | 3% | 0 a day, the least in 5 years | - |
| Operations | 47 | 4% | 5% | 2 a day, the most in 5 years | - |
| Operator, other | 60 | 5% | 7% | 2 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 175 |
| TG | Driver | 138 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 92 |
| TI | Traincrew rostering problem | 79 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 64 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 54 |
| MU | Depot operating problem | 45 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 45 |
| OS | Late start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident | 39 |
| XP | BRIDGE HIT | 36 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 7,925 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 3,583 |
| IA | Signal failure (including no fault found) | 2,981 |
| I1 | Overhead line/third rail defect | 2,355 |
| M8 | Technical failures above the Solebar | 2,342 |
| TI | Traincrew rostering problem | 2,328 |
| IB | Points failure (including no fault found) | 2,008 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,901 |
| IC | Track circuit failure (including no fault found) | 1,781 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 1,567 |