Langside
452 delay minutes
The biggest share (26%) of the delay picked up at Langside in the four weeks to 9 December 2023 came from how the network was run.
78% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 3 | <1% | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 29 | 6% | 16% | 1 a day, more than 2 of the other 4 years | 1 |
| Weather and structures | 69 | 15% | 7% | 2 a day, the most in 5 years | - |
| Autumn | 53 | 12% | 7% | 2 a day, more than 2 of the other 4 years | - |
| External | 5 | 1% | 4% | 0 a day, more than 1 of the other 4 years | - |
| Network management | 119 | 26% | 17% | 4 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 62 | 14% | 16% | 2 a day, more than 2 of the other 4 years | - |
| Traincrew | 45 | 10% | 11% | 2 a day, more than 2 of the other 4 years | - |
| Stations | 8 | 2% | 3% | 0 a day, the least in 5 years | - |
| Operations | 14 | 3% | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 47 | 10% | 7% | 2 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X9 | Points failure caused by severe snow or ice where heaters are fitted and working as designed | 66 |
| Q3 | NZ Pumps T | 44 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 41 |
| TG | Driver | 40 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 22 |
| ZU | No Cause Identified After investigation by both Parties | 22 |
| IP | Points failure caused by snow or frost where heaters are fitted but found to be not turned on, not operative or defective | 19 |
| M8 | Technical failures above the Solebar | 19 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 17 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 15 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 2,271 |
| TG | Driver | 1,855 |
| IB | Points failure (including no fault found) | 1,296 |
| ZU | No Cause Identified After investigation by both Parties | 1,010 |
| M8 | Technical failures above the Solebar | 761 |
| Q3 | NZ Pumps T | 684 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 658 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 609 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 589 |
| OU | Delays not Investigated by Network Rail | 471 |