1,917 delay minutes

The biggest share (34%) of the delay picked up at Littlehampton in the four weeks to 9 December 2023 came from signal, points and power faults.

87% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track1076%8% 4 a day, more than 2 of the other 4 years-
Signals, points and power64734%16% 23 a day, the most in 5 years1
Weather and structures1337%7% 5 a day, more than 3 of the other 4 years2
Autumn13<1%7% 0 a day, more than 1 of the other 4 years-
External19410%4% 7 a day, the most in 5 years7
Network management38120%17% 14 a day, more than 2 of the other 4 years16
The operators' causes
Train faults1035%16% 4 a day, more than 2 of the other 4 years1
Traincrew20211%11% 7 a day, more than 1 of the other 4 years6
Stations623%3% 2 a day, the most in 5 years-
Operations543%5% 2 a day, more than 3 of the other 4 years-
Operator, other211%7% 1 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)247
IBPoints failure (including no fault found)151
J0Telecom equipment radio failure (GSM-R)149
TGDriver147
XBVandalism or theft (including the placing of objects on the line)113
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)95
IISignalling lineside cable fault88
I1Overhead line/third rail defect79
XNRoad or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes)68
IRBroken/cracked/twisted/buckled/flawed rail54
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver8,472
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)5,727
OCSignaller including mis-routing (not ERTM /ETCS related)4,182
ICTrack circuit failure (including no fault found)3,782
TITraincrew rostering problem3,679
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,800
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure2,769
M8Technical failures above the Solebar2,767
IBPoints failure (including no fault found)2,400
OBDelayed by signaller not applying applicable regulating policy2,015