Llandudno
667 delay minutes
The biggest share (29%) of the delay picked up at Llandudno in the four weeks to 9 December 2023 came from traincrew problems.
89% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 11 | 2% | 8% | 0 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 73 | 11% | 16% | 3 a day, more than 1 of the other 4 years | 3 |
| Weather and structures | 6 | <1% | 7% | 0 a day, the least in 5 years | 1 |
| Autumn | 62 | 9% | 7% | 2 a day, the most in 5 years | - |
| External | 18 | 3% | 4% | 1 a day, the most in 5 years | - |
| Network management | 46 | 7% | 17% | 2 a day, the least in 5 years | - |
| The operators' causes | |||||
| Train faults | 166 | 25% | 16% | 6 a day, the most in 5 years | 11 |
| Traincrew | 191 | 29% | 11% | 7 a day, the most in 5 years | 4 |
| Stations | 44 | 7% | 3% | 2 a day, more than 3 of the other 4 years | - |
| Operations | 29 | 4% | 5% | 1 a day, more than 3 of the other 4 years | 2 |
| Operator, other | 22 | 3% | 7% | 1 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 118 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 97 |
| TH | (Senior) Conductor/Train Manager | 73 |
| T2 | Delay at unstaffed station to non-DOO train | 44 |
| QI | Cautioning due to railhead leaf contamination | 37 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 25 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 24 |
| Q3 | NZ Pumps T | 22 |
| TT | Leaf fall Neutral | 22 |
| J0 | Telecom equipment radio failure (GSM-R) | 18 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| T2 | Delay at unstaffed station to non-DOO train | 3,576 |
| ZY | Univestigated station overtime System Roll-up Only | 2,598 |
| TG | Driver | 2,093 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 1,878 |
| MD | Technical failures below the solebar | 1,559 |
| TH | (Senior) Conductor/Train Manager | 1,461 |
| OU | Delays not Investigated by Network Rail | 1,048 |
| M8 | Technical failures above the Solebar | 920 |
| TZ | Other Passenger Train Operating Company causes | 755 |
| M7 | Door and Door system faults | 638 |