286 delay minutes

Most of the delay picked up at Llandeilo in the four weeks to 9 December 2023 came from how the network was run.

9% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power228%16% 1 a day, more than 2 of the other 4 years-
Weather and structures--7% 0 a day, the least in 5 years-
Autumn--7% 0 a day, the least in 5 years-
External--4% 0 a day, the least in 5 years-
Network management16859%17% 6 a day, the most in 5 years-
The operators' causes
Train faults52%16% 0 a day, more than 3 of the other 4 years-
Traincrew3211%11% 1 a day, the most in 5 years-
Stations5921%3% 2 a day, the most in 5 years-
Operations--5% 0 a day, the least in 5 years-
Operator, other--7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
OTOps Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused)141
T2Delay at unstaffed station to non-DOO train59
TWDriver adhering to company professional driving standards or policy18
QAWTT schedule and or LTP Process including erroneous simplifiers16
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles11
IBPoints failure (including no fault found)8
JFOff track asset defects or issues on the NR network (not due to vandalism or weather or part of station infrastructure)7
TGDriver7
TH(Senior) Conductor/Train Manager7
M8Technical failures above the Solebar5
Since 2018
CodeWhat Network Rail loggedMinutes
OTOps Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused)2,849
T2Delay at unstaffed station to non-DOO train1,719
OZOther Network Rail operating causes587
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles525
TH(Senior) Conductor/Train Manager400
MDTechnical failures below the solebar305
IBPoints failure (including no fault found)206
TGDriver205
ILToken equipment failure (including no fault found)198
OUDelays not Investigated by Network Rail196