1,924 delay minutes

The biggest share (17%) of the delay picked up at Lenzie in the four weeks to 9 December 2023 came from faulty trains.

92% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track533%8% 2 a day, more than 3 of the other 4 years-
Signals, points and power21111%16% 8 a day, more than 2 of the other 4 years-
Weather and structures21011%7% 8 a day, more than 3 of the other 4 years-
Autumn22812%7% 8 a day, the most in 5 years-
External17<1%4% 1 a day, the least in 5 years-
Network management28515%17% 10 a day, more than 1 of the other 4 years-
The operators' causes
Train faults33617%16% 12 a day, more than 3 of the other 4 years-
Traincrew1447%11% 5 a day, more than 3 of the other 4 years-
Stations342%3% 1 a day, the least in 5 years-
Operations1307%5% 5 a day, more than 3 of the other 4 years-
Operator, other27814%7% 10 a day, the most in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Q3NZ Pumps T206
MPRail / wheel interface, adhesion problems (including ice on the running rail)183
TGDriver120
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions113
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)94
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)88
M8Technical failures above the Solebar77
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)70
MDTechnical failures below the solebar61
I2AC/DC trip (including no fault or cause found)49
Since 2018
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions10,023
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)7,131
TGDriver5,874
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)4,209
M8Technical failures above the Solebar4,008
MDTechnical failures below the solebar3,552
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.3,311
M7Door and Door system faults2,386
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure2,347
IBPoints failure (including no fault found)2,037