Leaves on the Line

Lockerbie

LOC Scotland route
CSV JSON

683 delay minutes

Most of the delay picked up at Lockerbie in the four weeks to 9 December 2023 came from faulty trains.

36% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power9314%16% 3 a day, more than 3 of the other 4 years-
Weather and structures477%7% 2 a day, more than 3 of the other 4 years-
Autumn5<1%7% 0 a day, more than 1 of the other 4 years-
External--4% 0 a day, the least in 5 years-
Network management355%17% 1 a day, more than 2 of the other 4 years-
The operators' causes
Train faults43063%16% 15 a day, the most in 5 years-
Traincrew172%11% 1 a day, the least in 5 years-
Stations4<1%3% 0 a day, more than 1 of the other 4 years-
Operations355%5% 1 a day, more than 2 of the other 4 years-
Operator, other172%7% 1 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
MBElectic Loco failure, defect, attention303
MNBrake and brake systems faults; including wheel flats where no other cause had been identified50
IHPower Supply And Distribution System Failure44
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure35
FOTime Lost en-route believed to be operator cause and information required from Operator (Ops Responsibility)27
NAOn train TASS/TILT failure23
MDTechnical failures below the solebar20
IBPoints failure (including no fault found)16
ICTrack circuit failure (including no fault found)16
TGDriver14
Since 2018
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions5,728
MBElectic Loco failure, defect, attention3,177
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,920
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure1,894
IRBroken/cracked/twisted/buckled/flawed rail1,722
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,677
IASignal failure (including no fault found)1,671
MCDiesel Loco failure, defect, attention1,483
MDTechnical failures below the solebar1,181
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail1,180