Larkhall
553 delay minutes
The biggest share (24%) of the delay picked up at Larkhall in the four weeks to 9 December 2023 came from autumn leaves.
95% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 12 | 2% | 8% | 0 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 32 | 6% | 16% | 1 a day, more than 1 of the other 4 years | 5 |
| Weather and structures | 42 | 8% | 7% | 2 a day, more than 3 of the other 4 years | 2 |
| Autumn | 132 | 24% | 7% | 5 a day, more than 3 of the other 4 years | - |
| External | 5 | <1% | 4% | 0 a day, more than 2 of the other 4 years | - |
| Network management | 55 | 10% | 17% | 2 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 88 | 16% | 16% | 3 a day, more than 3 of the other 4 years | 1 |
| Traincrew | 53 | 10% | 11% | 2 a day, more than 3 of the other 4 years | 2 |
| Stations | 11 | 2% | 3% | 0 a day, more than 3 of the other 4 years | - |
| Operations | 32 | 6% | 5% | 1 a day, more than 3 of the other 4 years | - |
| Operator, other | 92 | 17% | 7% | 3 a day, more than 3 of the other 4 years | 2 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 76 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 52 |
| QI | Cautioning due to railhead leaf contamination | 30 |
| TT | Leaf fall Neutral | 24 |
| OS | Late start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident | 22 |
| TG | Driver | 22 |
| FC | Freight Train Driver error, SPAD, Wrong routing or Missed AWS/DSD [No change] | 21 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 20 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 20 |
| QH | Adhesion problems due to leaf contamination | 16 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 1,923 |
| TG | Driver | 1,721 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 892 |
| IB | Points failure (including no fault found) | 863 |
| Q3 | NZ Pumps T | 850 |
| M8 | Technical failures above the Solebar | 710 |
| M7 | Door and Door system faults | 561 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 489 |
| VB | Vandalism or theft | 457 |
| IC | Track circuit failure (including no fault found) | 429 |