169 delay minutes
The biggest share (49%) of the delay picked up at Lydney in the four weeks to 9 December 2023 came from weather and structures.
11% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 29 | 17% | 8% | 1 a day, the most in 5 years | - |
| Signals, points and power | 3 | 2% | 16% | 0 a day, more than 3 of the other 4 years | - |
| Weather and structures | 82 | 49% | 7% | 3 a day, more than 3 of the other 4 years | 1 |
| Autumn | - | - | 7% | 0 a day, the least in 5 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 21 | 12% | 17% | 1 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 13 | 8% | 16% | 0 a day, more than 1 of the other 4 years | - |
| Traincrew | 11 | 7% | 11% | 0 a day, the most in 5 years | - |
| Stations | 10 | 6% | 3% | 0 a day, the most in 5 years | - |
| Operations | - | - | 5% | 0 a day, the least in 5 years | - |
| Operator, other | - | - | 7% | 0 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 82 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 29 |
| J9 | Preventative Maintenance to the infrastructure in response to a Remote Condition Monitoring Alert | 9 |
| I5 | Possession over-run from planned work | 8 |
| M9 | Reported fleet equipment defect - no fault found | 8 |
| TG | Driver | 8 |
| T2 | Delay at unstaffed station to non-DOO train | 7 |
| J5 | Infrastructure Asset fault reported but proven to be mistaken | 4 |
| ME | Steam locomotive failure/defect/attention | 4 |
| IC | Track circuit failure (including no fault found) | 3 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 25,993 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 345 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 263 |
| J3 | Axle Counter Failure | 258 |
| I8 | Animal Strike or Incursion within the control of Network Rail | 253 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 247 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 192 |
| JG | ESR/TSR Work not comp/canx pssn (restriction did not exist prior to pssn) | 185 |
| IK | Telecom equipment failure (including no fault found) | 169 |
| MD | Technical failures below the solebar | 153 |