Machynlleth
971 delay minutes
The biggest share (23%) of the delay picked up at Machynlleth in the four weeks to 9 December 2023 came from faulty trains.
70% of these minutes were knock-on from something that happened elsewhere first. 80% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 115 | 12% | 16% | 4 a day, more than 3 of the other 4 years | - |
| Weather and structures | 50 | 5% | 7% | 2 a day, more than 3 of the other 4 years | 7 |
| Autumn | 179 | 18% | 7% | 6 a day, the most in 5 years | - |
| External | 6 | <1% | 4% | 0 a day, more than 2 of the other 4 years | 2 |
| Network management | 158 | 16% | 17% | 6 a day, the most in 5 years | 20 |
| The operators' causes | |||||
| Train faults | 226 | 23% | 16% | 8 a day, more than 3 of the other 4 years | 22 |
| Traincrew | 140 | 14% | 11% | 5 a day, the most in 5 years | 2 |
| Stations | 3 | <1% | 3% | 0 a day, the least in 5 years | - |
| Operations | 67 | 7% | 5% | 2 a day, more than 3 of the other 4 years | 6 |
| Operator, other | 27 | 3% | 7% | 1 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| QH | Adhesion problems due to leaf contamination | 103 |
| TG | Driver | 89 |
| M7 | Door and Door system faults | 77 |
| QI | Cautioning due to railhead leaf contamination | 67 |
| TZ | Other Passenger Train Operating Company causes | 67 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 48 |
| TH | (Senior) Conductor/Train Manager | 48 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 47 |
| IC | Track circuit failure (including no fault found) | 39 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 38 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 4,294 |
| MD | Technical failures below the solebar | 3,974 |
| M8 | Technical failures above the Solebar | 3,690 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 3,687 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 3,180 |
| TG | Driver | 2,720 |
| TZ | Other Passenger Train Operating Company causes | 2,480 |
| OU | Delays not Investigated by Network Rail | 1,844 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 1,441 |
| J0 | Telecom equipment radio failure (GSM-R) | 1,409 |