Leaves on the Line

Mallaig

MLG Scotland route
CSV JSON

231 delay minutes

Most of the delay picked up at Mallaig in the four weeks to 9 December 2023 came from weather and structures.

45% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track7432%8% 3 a day, the most in 5 years-
Signals, points and power--16% 0 a day, the least in 5 years-
Weather and structures13860%7% 5 a day, the most in 5 years-
Autumn--7% 0 a day, the least in 5 years-
External52%4% 0 a day, the most in 5 years-
Network management94%17% 0 a day, more than 2 of the other 4 years-
The operators' causes
Train faults42%16% 0 a day, more than 1 of the other 4 years-
Traincrew--11% 0 a day, the least in 5 years-
Stations1<1%3% 0 a day, the most in 5 years-
Operations--5% 0 a day, the least in 5 years-
Operator, other--7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions78
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure60
JATSR speed restrictions for track work outside of the Timetable Planning Rules45
JSCondition of Track TSR outside the Timetable Planning Rules29
ZUNo Cause Identified After investigation by both Parties9
XKNational Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed)5
M8Technical failures above the Solebar4
RBPassengers joining/alighting1
Since 2018
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions5,677
ZUNo Cause Identified After investigation by both Parties864
MDTechnical failures below the solebar587
M8Technical failures above the Solebar467
TGDriver422
M7Door and Door system faults409
RMWaiting connections from other transport modes308
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure252
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail244
RBPassengers joining/alighting212