Motherwell
2,362 delay minutes
The biggest share (24%) of the delay picked up at Motherwell in the four weeks to 9 December 2023 came from faulty trains.
69% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 205 | 9% | 8% | 7 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 156 | 7% | 16% | 6 a day, more than 2 of the other 4 years | 9 |
| Weather and structures | 175 | 7% | 7% | 6 a day, more than 3 of the other 4 years | 13 |
| Autumn | 233 | 10% | 7% | 8 a day, more than 3 of the other 4 years | - |
| External | 173 | 7% | 4% | 6 a day, the most in 5 years | 1 |
| Network management | 252 | 11% | 17% | 9 a day, more than 2 of the other 4 years | 52 |
| The operators' causes | |||||
| Train faults | 575 | 24% | 16% | 21 a day, the most in 5 years | 13 |
| Traincrew | 225 | 10% | 11% | 8 a day, more than 2 of the other 4 years | 4 |
| Stations | 54 | 2% | 3% | 2 a day, more than 3 of the other 4 years | - |
| Operations | 82 | 3% | 5% | 3 a day, more than 1 of the other 4 years | 1 |
| Operator, other | 234 | 10% | 7% | 8 a day, more than 2 of the other 4 years | 4 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 191 |
| Q3 | NZ Pumps T | 179 |
| TG | Driver | 173 |
| XE | GSM-R call raised outside Network Rail network (by a non-track access party and/or for a legitimate safety issue) | 164 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 164 |
| M8 | Technical failures above the Solebar | 157 |
| X9 | Points failure caused by severe snow or ice where heaters are fitted and working as designed | 118 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 106 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 88 |
| TT | Leaf fall Neutral | 76 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 8,607 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 5,825 |
| IB | Points failure (including no fault found) | 3,660 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 3,505 |
| M8 | Technical failures above the Solebar | 3,322 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 2,850 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,711 |
| Q3 | NZ Pumps T | 2,388 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 2,369 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 2,277 |