Montrose
1,007 delay minutes
The biggest share (43%) of the delay picked up at Montrose in the four weeks to 9 December 2023 came from weather and structures.
43% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 21 | 2% | 8% | 1 a day, more than 2 of the other 4 years | 5 |
| Signals, points and power | 252 | 25% | 16% | 9 a day, the most in 5 years | 2 |
| Weather and structures | 431 | 43% | 7% | 15 a day, more than 3 of the other 4 years | - |
| Autumn | 7 | <1% | 7% | 0 a day, the least in 5 years | - |
| External | 49 | 5% | 4% | 2 a day, more than 3 of the other 4 years | - |
| Network management | 62 | 6% | 17% | 2 a day, more than 1 of the other 4 years | 32 |
| The operators' causes | |||||
| Train faults | 91 | 9% | 16% | 3 a day, more than 3 of the other 4 years | 6 |
| Traincrew | 70 | 7% | 11% | 2 a day, the most in 5 years | 1 |
| Stations | 13 | 1% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | 6 | <1% | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 7 | <1% | 7% | 0 a day, the least in 5 years | 2 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 294 |
| IA | Signal failure (including no fault found) | 166 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 120 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 66 |
| TG | Driver | 56 |
| MW | Weather - effect on T&RS equipment | 36 |
| MD | Technical failures below the solebar | 33 |
| XP | BRIDGE HIT | 31 |
| ZU | No Cause Identified After investigation by both Parties | 19 |
| XR | Cable vandalism or theft | 18 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 3,884 |
| ZU | No Cause Identified After investigation by both Parties | 2,152 |
| MD | Technical failures below the solebar | 2,115 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 2,054 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,899 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 1,844 |
| TG | Driver | 1,803 |
| M8 | Technical failures above the Solebar | 1,699 |
| OL | Signal Box not open during booked hours | 1,521 |
| IA | Signal failure (including no fault found) | 1,489 |