Leaves on the Line

Montrose

MTS Scotland route
CSV JSON

1,007 delay minutes

The biggest share (43%) of the delay picked up at Montrose in the four weeks to 9 December 2023 came from weather and structures.

43% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track212%8% 1 a day, more than 2 of the other 4 years5
Signals, points and power25225%16% 9 a day, the most in 5 years2
Weather and structures43143%7% 15 a day, more than 3 of the other 4 years-
Autumn7<1%7% 0 a day, the least in 5 years-
External495%4% 2 a day, more than 3 of the other 4 years-
Network management626%17% 2 a day, more than 1 of the other 4 years32
The operators' causes
Train faults919%16% 3 a day, more than 3 of the other 4 years6
Traincrew707%11% 2 a day, the most in 5 years1
Stations131%3% 0 a day, more than 1 of the other 4 years-
Operations6<1%5% 0 a day, the least in 5 years-
Operator, other7<1%7% 0 a day, the least in 5 years2

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions294
IASignal failure (including no fault found)166
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure120
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure66
TGDriver56
MWWeather - effect on T&RS equipment36
MDTechnical failures below the solebar33
XPBRIDGE HIT31
ZUNo Cause Identified After investigation by both Parties19
XRCable vandalism or theft18
Since 2018
CodeWhat Network Rail loggedMinutes
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)3,884
ZUNo Cause Identified After investigation by both Parties2,152
MDTechnical failures below the solebar2,115
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions2,054
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,899
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure1,844
TGDriver1,803
M8Technical failures above the Solebar1,699
OLSignal Box not open during booked hours1,521
IASignal failure (including no fault found)1,489