New Barnet
34 delay minutes
Most of the delay picked up at New Barnet in the four weeks to 9 December 2023 came from how the network was run.
47% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | - | - | 16% | - |
| Weather and structures | - | - | 7% | - |
| Autumn | - | - | 7% | - |
| External | - | - | 4% | - |
| Network management | 30 | 88% | 17% | 3 |
| The operators' causes | ||||
| Train faults | 4 | 12% | 16% | - |
| Traincrew | - | - | 11% | - |
| Stations | - | - | 3% | - |
| Operations | - | - | 5% | - |
| Operator, other | - | - | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| I5 | Possession over-run from planned work | 30 |
| MV | Engineers on-track equipment failure outside possession | 4 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| J5 | Infrastructure Asset fault reported but proven to be mistaken | 104 |
| TG | Driver | 68 |
| I5 | Possession over-run from planned work | 60 |
| I1 | Overhead line/third rail defect | 53 |
| R3 | Station Staff unavailable - missing or uncovered | 53 |
| QM | Train schedule/STP Process including erroneous simplifiers | 34 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 26 |
| I9 | Fires starting on Network Rail Infrastructure | 22 |
| MU | Depot operating problem | 13 |
| MD | Technical failures below the solebar | 11 |