Leaves on the Line

North Berwick

NBW Scotland route
CSV JSON

577 delay minutes

The biggest share (21%) of the delay picked up at North Berwick in the four weeks to 9 December 2023 came from weather and structures.

97% of these minutes were knock-on from something that happened elsewhere first. 91% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track437%8% 2 a day, more than 2 of the other 4 years-
Signals, points and power7413%16% 3 a day, more than 1 of the other 4 years-
Weather and structures11921%7% 4 a day, more than 3 of the other 4 years-
Autumn132%7% 0 a day, more than 2 of the other 4 years-
External102%4% 0 a day, more than 2 of the other 4 years-
Network management10418%17% 4 a day, more than 3 of the other 4 years1
The operators' causes
Train faults7513%16% 3 a day, more than 2 of the other 4 years-
Traincrew9817%11% 4 a day, the most in 5 years2
Stations112%3% 0 a day, more than 1 of the other 4 years-
Operations193%5% 1 a day, more than 2 of the other 4 years-
Operator, other122%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver89
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)70
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.43
IISignalling lineside cable fault30
JKFlooding not due to exceptional weather26
MUDepot operating problem25
MNBrake and brake systems faults; including wheel flats where no other cause had been identified20
I5Possession over-run from planned work19
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions19
OUDelays not Investigated by Network Rail18
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver1,844
MDTechnical failures below the solebar829
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.812
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions712
M8Technical failures above the Solebar703
I1Overhead line/third rail defect685
IBPoints failure (including no fault found)673
JBReactionary Delay to 'P' coded TSRs634
MUDepot operating problem619
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)566