North Berwick
577 delay minutes
The biggest share (21%) of the delay picked up at North Berwick in the four weeks to 9 December 2023 came from weather and structures.
97% of these minutes were knock-on from something that happened elsewhere first. 91% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 43 | 7% | 8% | 2 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 74 | 13% | 16% | 3 a day, more than 1 of the other 4 years | - |
| Weather and structures | 119 | 21% | 7% | 4 a day, more than 3 of the other 4 years | - |
| Autumn | 13 | 2% | 7% | 0 a day, more than 2 of the other 4 years | - |
| External | 10 | 2% | 4% | 0 a day, more than 2 of the other 4 years | - |
| Network management | 104 | 18% | 17% | 4 a day, more than 3 of the other 4 years | 1 |
| The operators' causes | |||||
| Train faults | 75 | 13% | 16% | 3 a day, more than 2 of the other 4 years | - |
| Traincrew | 98 | 17% | 11% | 4 a day, the most in 5 years | 2 |
| Stations | 11 | 2% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | 19 | 3% | 5% | 1 a day, more than 2 of the other 4 years | - |
| Operator, other | 12 | 2% | 7% | 0 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 89 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 70 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 43 |
| II | Signalling lineside cable fault | 30 |
| JK | Flooding not due to exceptional weather | 26 |
| MU | Depot operating problem | 25 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 20 |
| I5 | Possession over-run from planned work | 19 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 19 |
| OU | Delays not Investigated by Network Rail | 18 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 1,844 |
| MD | Technical failures below the solebar | 829 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 812 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 712 |
| M8 | Technical failures above the Solebar | 703 |
| I1 | Overhead line/third rail defect | 685 |
| IB | Points failure (including no fault found) | 673 |
| JB | Reactionary Delay to 'P' coded TSRs | 634 |
| MU | Depot operating problem | 619 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 566 |