Leaves on the Line

Newcraighall

NEW Scotland route
CSV JSON

713 delay minutes

The biggest share (18%) of the delay picked up at Newcraighall in the four weeks to 9 December 2023 came from faulty trains.

86% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track172%8% 1 a day, the least in 5 years-
Signals, points and power436%16% 2 a day, more than 1 of the other 4 years-
Weather and structures8312%7% 3 a day, more than 2 of the other 4 years-
Autumn274%7% 1 a day, the least in 5 years-
External294%4% 1 a day, more than 1 of the other 4 years-
Network management9113%17% 3 a day, more than 1 of the other 4 years-
The operators' causes
Train faults12818%16% 5 a day, more than 1 of the other 4 years-
Traincrew8111%11% 3 a day, more than 1 of the other 4 years-
Stations11516%3% 4 a day, the most in 5 years-
Operations7410%5% 3 a day, more than 3 of the other 4 years-
Operator, other264%7% 1 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver72
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)59
RQUn-booked assistance for a person with reduced mobility joining/alighting,45
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)41
MUDepot operating problem36
M8Technical failures above the Solebar29
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)29
RBPassengers joining/alighting24
Q3NZ Pumps T21
M1Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC)20
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver3,495
MDTechnical failures below the solebar3,325
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)2,732
M8Technical failures above the Solebar1,546
MUDepot operating problem1,281
MNBrake and brake systems faults; including wheel flats where no other cause had been identified1,119
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.954
RQUn-booked assistance for a person with reduced mobility joining/alighting,902
M7Door and Door system faults883
RBPassengers joining/alighting867