Newark North Gate
3,542 delay minutes
Most of the delay picked up at Newark North Gate in the four weeks to 9 December 2023 came from signal, points and power faults.
24% of these minutes were knock-on from something that happened elsewhere first. 34% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 66 | 2% | 8% | 2 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 2,661 | 75% | 16% | 95 a day, the most in 5 years | 4 |
| Weather and structures | 86 | 2% | 7% | 3 a day, more than 3 of the other 4 years | - |
| Autumn | 101 | 3% | 7% | 4 a day, the most in 5 years | - |
| External | 69 | 2% | 4% | 2 a day, more than 2 of the other 4 years | - |
| Network management | 179 | 5% | 17% | 6 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 214 | 6% | 16% | 8 a day, more than 2 of the other 4 years | - |
| Traincrew | 39 | 1% | 11% | 1 a day, more than 1 of the other 4 years | 1 |
| Stations | 36 | 1% | 3% | 1 a day, more than 2 of the other 4 years | - |
| Operations | 62 | 2% | 5% | 2 a day, more than 3 of the other 4 years | - |
| Operator, other | 31 | <1% | 7% | 1 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| I1 | Overhead line/third rail defect | 2,466 |
| QJ | Special working for leaf-fall track circuit operation | 91 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 85 |
| II | Signalling lineside cable fault | 58 |
| OU | Delays not Investigated by Network Rail | 58 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 58 |
| I8 | Animal Strike or Incursion within the control of Network Rail | 44 |
| IA | Signal failure (including no fault found) | 40 |
| M7 | Door and Door system faults | 33 |
| TG | Driver | 32 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| I1 | Overhead line/third rail defect | 6,299 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 5,421 |
| IB | Points failure (including no fault found) | 4,548 |
| MD | Technical failures below the solebar | 3,700 |
| MB | Electic Loco failure, defect, attention | 3,184 |
| II | Signalling lineside cable fault | 2,858 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 2,688 |
| IC | Track circuit failure (including no fault found) | 2,685 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 2,656 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 2,434 |