Leaves on the Line

Neath

NTH Wales route
CSV JSON

989 delay minutes

The biggest share (36%) of the delay picked up at Neath in the four weeks to 9 December 2023 came from faulty trains.

70% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track657%8% 2 a day, the most in 5 years-
Signals, points and power859%16% 3 a day, the most in 5 years-
Weather and structures303%7% 1 a day, more than 3 of the other 4 years-
Autumn10<1%7% 0 a day, more than 2 of the other 4 years-
External6<1%4% 0 a day, more than 3 of the other 4 years-
Network management869%17% 3 a day, more than 3 of the other 4 years-
The operators' causes
Train faults35836%16% 13 a day, the most in 5 years-
Traincrew15115%11% 5 a day, the most in 5 years-
Stations9710%3% 3 a day, the most in 5 years-
Operations10010%5% 4 a day, the most in 5 years-
Operator, other3<1%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps178
TGDriver103
T2Delay at unstaffed station to non-DOO train74
M8Technical failures above the Solebar70
TRTrain Operating Company Directive55
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.45
TZOther Passenger Train Operating Company causes37
OCSignaller including mis-routing (not ERTM /ETCS related)36
MDTechnical failures below the solebar33
TITraincrew rostering problem27
Since 2018
CodeWhat Network Rail loggedMinutes
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)2,991
MDTechnical failures below the solebar2,129
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps1,619
TGDriver1,556
T2Delay at unstaffed station to non-DOO train1,105
J3Axle Counter Failure1,084
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure934
M8Technical failures above the Solebar869
OUDelays not Investigated by Network Rail861
OCSignaller including mis-routing (not ERTM /ETCS related)771