Leaves on the Line

Northallerton

NTR East Coast route
CSV JSON

2,645 delay minutes

The biggest share (35%) of the delay picked up at Northallerton in the four weeks to 9 December 2023 came from weather and structures.

58% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track2198%8% 8 a day, more than 2 of the other 4 years-
Signals, points and power2479%16% 9 a day, more than 2 of the other 4 years-
Weather and structures92635%7% 33 a day, the most in 5 years-
Autumn472%7% 2 a day, more than 2 of the other 4 years-
External542%4% 2 a day, the least in 5 years-
Network management30912%17% 11 a day, more than 2 of the other 4 years1
The operators' causes
Train faults46418%16% 17 a day, more than 2 of the other 4 years-
Traincrew1757%11% 6 a day, more than 2 of the other 4 years-
Stations703%3% 3 a day, more than 3 of the other 4 years-
Operations703%5% 3 a day, more than 3 of the other 4 years-
Operator, other642%7% 2 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)690
MWWeather - effect on T&RS equipment191
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.175
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions132
TGDriver112
OUDelays not Investigated by Network Rail107
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail72
IKTelecom equipment failure (including no fault found)59
IBPoints failure (including no fault found)58
MDTechnical failures below the solebar49
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver5,507
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.4,707
MDTechnical failures below the solebar4,145
IBPoints failure (including no fault found)3,703
M8Technical failures above the Solebar3,529
JSCondition of Track TSR outside the Timetable Planning Rules3,515
I1Overhead line/third rail defect3,140
MNBrake and brake systems faults; including wheel flats where no other cause had been identified2,984
ICTrack circuit failure (including no fault found)2,592
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)2,315