Northallerton
2,645 delay minutes
The biggest share (35%) of the delay picked up at Northallerton in the four weeks to 9 December 2023 came from weather and structures.
58% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 219 | 8% | 8% | 8 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 247 | 9% | 16% | 9 a day, more than 2 of the other 4 years | - |
| Weather and structures | 926 | 35% | 7% | 33 a day, the most in 5 years | - |
| Autumn | 47 | 2% | 7% | 2 a day, more than 2 of the other 4 years | - |
| External | 54 | 2% | 4% | 2 a day, the least in 5 years | - |
| Network management | 309 | 12% | 17% | 11 a day, more than 2 of the other 4 years | 1 |
| The operators' causes | |||||
| Train faults | 464 | 18% | 16% | 17 a day, more than 2 of the other 4 years | - |
| Traincrew | 175 | 7% | 11% | 6 a day, more than 2 of the other 4 years | - |
| Stations | 70 | 3% | 3% | 3 a day, more than 3 of the other 4 years | - |
| Operations | 70 | 3% | 5% | 3 a day, more than 3 of the other 4 years | - |
| Operator, other | 64 | 2% | 7% | 2 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 690 |
| MW | Weather - effect on T&RS equipment | 191 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 175 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 132 |
| TG | Driver | 112 |
| OU | Delays not Investigated by Network Rail | 107 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 72 |
| IK | Telecom equipment failure (including no fault found) | 59 |
| IB | Points failure (including no fault found) | 58 |
| MD | Technical failures below the solebar | 49 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 5,507 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 4,707 |
| MD | Technical failures below the solebar | 4,145 |
| IB | Points failure (including no fault found) | 3,703 |
| M8 | Technical failures above the Solebar | 3,529 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 3,515 |
| I1 | Overhead line/third rail defect | 3,140 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 2,984 |
| IC | Track circuit failure (including no fault found) | 2,592 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 2,315 |