Leaves on the Line

Newhaven Harbour

NVH Sussex route
CSV JSON

3 delay minutes

Most of the delay picked up at Newhaven Harbour in the four weeks to 9 December 2023 came from traincrew problems.

0% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew3100%11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver3
Since 2018
CodeWhat Network Rail loggedMinutes
ICTrack circuit failure (including no fault found)79
TGDriver68
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.62
MDTechnical failures below the solebar56
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure38
JKFlooding not due to exceptional weather37
I1Overhead line/third rail defect34
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles33
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)31
T3Waiting connections from other transport modes20