Old Street
100 delay minutes
The biggest share (31%) of the delay picked up at Old Street in the four weeks to 9 December 2023 came from signal, points and power faults.
69% of these minutes were knock-on from something that happened elsewhere first. 94% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 31 | 31% | 16% | 1 a day, more than 2 of the other 4 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 5 | 5% | 7% | 0 a day, more than 1 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 25 | 25% | 17% | 1 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 19 | 19% | 16% | 1 a day, the least in 5 years | - |
| Traincrew | 8 | 8% | 11% | 0 a day, the least in 5 years | - |
| Stations | 3 | 3% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | - | - | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 9 | 9% | 7% | 0 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IJ | AWS/ATP/TPWS/Train stop/On track equipment failure | 11 |
| M7 | Door and Door system faults | 11 |
| I2 | AC/DC trip (including no fault or cause found) | 9 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 9 |
| M8 | Technical failures above the Solebar | 8 |
| TG | Driver | 8 |
| J0 | Telecom equipment radio failure (GSM-R) | 6 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 5 |
| OR | LOM directive or Signaller correctly applying local instructions (ex late running trains or infrastructure Accepted Limitation) | 5 |
| VB | Vandalism or theft | 4 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 6,217 |
| MD | Technical failures below the solebar | 1,960 |
| TI | Traincrew rostering problem | 1,472 |
| M8 | Technical failures above the Solebar | 1,340 |
| IA | Signal failure (including no fault found) | 1,007 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 773 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 650 |
| IJ | AWS/ATP/TPWS/Train stop/On track equipment failure | 600 |
| IC | Track circuit failure (including no fault found) | 595 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 550 |