820 delay minutes

The biggest share (37%) of the delay picked up at Oxted in the four weeks to 9 December 2023 came from how the network was run.

73% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track263%8% 1 a day, more than 2 of the other 4 years-
Signals, points and power25231%16% 9 a day, more than 3 of the other 4 years6
Weather and structures3<1%7% 0 a day, the least in 5 years-
Autumn273%7% 1 a day, more than 2 of the other 4 years-
External8<1%4% 0 a day, more than 2 of the other 4 years-
Network management30137%17% 11 a day, more than 3 of the other 4 years7
The operators' causes
Train faults739%16% 3 a day, more than 3 of the other 4 years2
Traincrew526%11% 2 a day, more than 1 of the other 4 years1
Stations233%3% 1 a day, more than 3 of the other 4 years-
Operations3<1%5% 0 a day, more than 2 of the other 4 years1
Operator, other536%7% 2 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)161
IBPoints failure (including no fault found)127
OCSignaller including mis-routing (not ERTM /ETCS related)44
OBDelayed by signaller not applying applicable regulating policy35
ICTrack circuit failure (including no fault found)31
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure29
MYCoupler, Coupler system and Jumper cable faults29
TGDriver29
J0Telecom equipment radio failure (GSM-R)28
VHPassenger Communication cord, door egress or emergency train alarm operated24
Since 2018
CodeWhat Network Rail loggedMinutes
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)7,009
TGDriver2,746
ICTrack circuit failure (including no fault found)2,172
OCSignaller including mis-routing (not ERTM /ETCS related)2,151
OBDelayed by signaller not applying applicable regulating policy2,109
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,969
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,494
IRBroken/cracked/twisted/buckled/flawed rail1,241
M8Technical failures above the Solebar1,135
IBPoints failure (including no fault found)801