Leaves on the Line

Pilning

PIL Wales route
CSV JSON

460 delay minutes

The biggest share (21%) of the delay picked up at Pilning in the four weeks to 9 December 2023 came from faulty trains.

83% of these minutes were knock-on from something that happened elsewhere first. 90% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track6614%8% 2 a day, the most in 5 years-
Signals, points and power5813%16% 2 a day, more than 3 of the other 4 years-
Weather and structures5312%7% 2 a day, the most in 5 years-
Autumn4<1%7% 0 a day, the least in 5 years-
External--4% 0 a day, the least in 5 years-
Network management7516%17% 3 a day, more than 2 of the other 4 years-
The operators' causes
Train faults9521%16% 3 a day, the most in 5 years-
Traincrew5111%11% 2 a day, the most in 5 years-
Stations143%3% 1 a day, more than 3 of the other 4 years-
Operations296%5% 1 a day, the most in 5 years-
Operator, other174%7% 1 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure49
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.41
TGDriver36
OCSignaller including mis-routing (not ERTM /ETCS related)22
M7Door and Door system faults18
M8Technical failures above the Solebar18
IASignal failure (including no fault found)16
OUDelays not Investigated by Network Rail14
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps12
FHFOC Planning issue (not diagramming or rostering)11
Since 2018
CodeWhat Network Rail loggedMinutes
JSCondition of Track TSR outside the Timetable Planning Rules2,852
J3Axle Counter Failure2,314
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,554
IBPoints failure (including no fault found)1,417
I1Overhead line/third rail defect1,114
OCSignaller including mis-routing (not ERTM /ETCS related)1,088
TGDriver960
OUDelays not Investigated by Network Rail730
MDTechnical failures below the solebar716
QMTrain schedule/STP Process including erroneous simplifiers672