Pilning
460 delay minutes
The biggest share (21%) of the delay picked up at Pilning in the four weeks to 9 December 2023 came from faulty trains.
83% of these minutes were knock-on from something that happened elsewhere first. 90% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 66 | 14% | 8% | 2 a day, the most in 5 years | - |
| Signals, points and power | 58 | 13% | 16% | 2 a day, more than 3 of the other 4 years | - |
| Weather and structures | 53 | 12% | 7% | 2 a day, the most in 5 years | - |
| Autumn | 4 | <1% | 7% | 0 a day, the least in 5 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 75 | 16% | 17% | 3 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 95 | 21% | 16% | 3 a day, the most in 5 years | - |
| Traincrew | 51 | 11% | 11% | 2 a day, the most in 5 years | - |
| Stations | 14 | 3% | 3% | 1 a day, more than 3 of the other 4 years | - |
| Operations | 29 | 6% | 5% | 1 a day, the most in 5 years | - |
| Operator, other | 17 | 4% | 7% | 1 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 49 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 41 |
| TG | Driver | 36 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 22 |
| M7 | Door and Door system faults | 18 |
| M8 | Technical failures above the Solebar | 18 |
| IA | Signal failure (including no fault found) | 16 |
| OU | Delays not Investigated by Network Rail | 14 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 12 |
| FH | FOC Planning issue (not diagramming or rostering) | 11 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JS | Condition of Track TSR outside the Timetable Planning Rules | 2,852 |
| J3 | Axle Counter Failure | 2,314 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,554 |
| IB | Points failure (including no fault found) | 1,417 |
| I1 | Overhead line/third rail defect | 1,114 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,088 |
| TG | Driver | 960 |
| OU | Delays not Investigated by Network Rail | 730 |
| MD | Technical failures below the solebar | 716 |
| QM | Train schedule/STP Process including erroneous simplifiers | 672 |