Leaves on the Line

Pembroke Dock

PMD Wales route
CSV JSON

401 delay minutes

The biggest share (33%) of the delay picked up at Pembroke Dock in the four weeks to 9 December 2023 came from faulty trains.

75% of these minutes were knock-on from something that happened elsewhere first. 94% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track307%8% 1 a day, more than 3 of the other 4 years-
Signals, points and power338%16% 1 a day, more than 3 of the other 4 years-
Weather and structures133%7% 0 a day, more than 3 of the other 4 years3
Autumn369%7% 1 a day, the most in 5 years-
External195%4% 1 a day, the most in 5 years-
Network management1<1%17% 0 a day, the least in 5 years2
The operators' causes
Train faults13333%16% 5 a day, the most in 5 years4
Traincrew5213%11% 2 a day, the most in 5 years5
Stations338%3% 1 a day, more than 3 of the other 4 years-
Operations236%5% 1 a day, more than 3 of the other 4 years-
Operator, other297%7% 1 a day, the most in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps84
TH(Senior) Conductor/Train Manager36
T2Delay at unstaffed station to non-DOO train33
QHAdhesion problems due to leaf contamination32
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.30
MNBrake and brake systems faults; including wheel flats where no other cause had been identified28
VETicket irregularities or refusals to pay20
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)19
XKNational Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed)19
IISignalling lineside cable fault16
Since 2018
CodeWhat Network Rail loggedMinutes
T2Delay at unstaffed station to non-DOO train1,261
TGDriver890
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps796
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)702
MDTechnical failures below the solebar671
TH(Senior) Conductor/Train Manager590
OUDelays not Investigated by Network Rail538
M8Technical failures above the Solebar461
TZOther Passenger Train Operating Company causes385
IBPoints failure (including no fault found)309