Leaves on the Line

Prestonpans

PST Scotland route
CSV JSON

12 delay minutes

Most of the delay picked up at Prestonpans in the four weeks to 9 December 2023 came from how the network was run.

100% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management12100%17%1
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
I5Possession over-run from planned work12
Since 2018
CodeWhat Network Rail loggedMinutes
I1Overhead line/third rail defect73
MNBrake and brake systems faults; including wheel flats where no other cause had been identified27
M8Technical failures above the Solebar19
IBPoints failure (including no fault found)18
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure17
MUDepot operating problem17
MDTechnical failures below the solebar16
TXDelays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays)16
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)14
I2AC/DC trip (including no fault or cause found)14