Port Talbot Parkway
1,676 delay minutes
The biggest share (29%) of the delay picked up at Port Talbot Parkway in the four weeks to 9 December 2023 came from faulty trains.
51% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 71 | 4% | 8% | 3 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 151 | 9% | 16% | 5 a day, more than 3 of the other 4 years | - |
| Weather and structures | 9 | <1% | 7% | 0 a day, more than 1 of the other 4 years | - |
| Autumn | 38 | 2% | 7% | 1 a day, the most in 5 years | - |
| External | 13 | <1% | 4% | 0 a day, more than 3 of the other 4 years | - |
| Network management | 399 | 24% | 17% | 14 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 493 | 29% | 16% | 18 a day, the most in 5 years | 1 |
| Traincrew | 214 | 13% | 11% | 8 a day, the most in 5 years | 1 |
| Stations | 141 | 8% | 3% | 5 a day, the most in 5 years | - |
| Operations | 90 | 5% | 5% | 3 a day, more than 3 of the other 4 years | 1 |
| Operator, other | 58 | 3% | 7% | 2 a day, the most in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 196 |
| TG | Driver | 150 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 120 |
| MC | Diesel Loco failure, defect, attention | 117 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 94 |
| T2 | Delay at unstaffed station to non-DOO train | 85 |
| TZ | Other Passenger Train Operating Company causes | 79 |
| Q1 | Takeback Pumps | 73 |
| M8 | Technical failures above the Solebar | 61 |
| IC | Track circuit failure (including no fault found) | 59 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 4,618 |
| MD | Technical failures below the solebar | 3,350 |
| TG | Driver | 2,899 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 2,799 |
| T2 | Delay at unstaffed station to non-DOO train | 2,665 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,999 |
| IC | Track circuit failure (including no fault found) | 1,732 |
| M8 | Technical failures above the Solebar | 1,725 |
| IB | Points failure (including no fault found) | 1,621 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 1,512 |