Prestwick
425 delay minutes
The biggest share (44%) of the delay picked up at Prestwick in the four weeks to 9 December 2023 came from how the network was run.
73% of these minutes were knock-on from something that happened elsewhere first. 88% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | 58 | 14% | 16% | - |
| Weather and structures | 13 | 3% | 7% | 1 |
| Autumn | 25 | 6% | 7% | - |
| External | - | - | 4% | - |
| Network management | 189 | 44% | 17% | 82 |
| The operators' causes | ||||
| Train faults | 61 | 14% | 16% | - |
| Traincrew | 43 | 10% | 11% | - |
| Stations | 18 | 4% | 3% | - |
| Operations | 6 | 1% | 5% | - |
| Operator, other | 12 | 3% | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 52 |
| QM | Train schedule/STP Process including erroneous simplifiers | 45 |
| TG | Driver | 43 |
| J8 | OTM DAMAGE | 36 |
| M7 | Door and Door system faults | 31 |
| IA | Signal failure (including no fault found) | 26 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 26 |
| OE | Failure to lay Sandite or operate Railhead Conditioning train as programmed | 23 |
| IC | Track circuit failure (including no fault found) | 14 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 14 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 332 |
| QM | Train schedule/STP Process including erroneous simplifiers | 163 |
| IA | Signal failure (including no fault found) | 156 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 110 |
| IC | Track circuit failure (including no fault found) | 106 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 61 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 55 |
| Q3 | NZ Pumps T | 55 |
| M7 | Door and Door system faults | 54 |
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 52 |