Leaves on the Line

Royston

RYS East Coast route
CSV JSON

2,405 delay minutes

The biggest share (36%) of the delay picked up at Royston in the four weeks to 9 December 2023 came from how the network was run.

66% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track1356%8% 5 a day, more than 1 of the other 4 years-
Signals, points and power28712%16% 10 a day, more than 3 of the other 4 years2
Weather and structures372%7% 1 a day, more than 3 of the other 4 years-
Autumn623%7% 2 a day, more than 2 of the other 4 years-
External1325%4% 5 a day, more than 2 of the other 4 years1
Network management87336%17% 31 a day, the most in 5 years8
The operators' causes
Train faults2018%16% 7 a day, more than 3 of the other 4 years4
Traincrew41017%11% 15 a day, more than 3 of the other 4 years5
Stations683%3% 2 a day, the most in 5 years-
Operations532%5% 2 a day, the most in 5 years-
Operator, other1486%7% 5 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver327
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)265
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure215
OKDelay caused by Operating staff oversight, issues or absence (excluding signallers and Control)184
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.117
XPBRIDGE HIT88
M7Door and Door system faults81
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)77
OUDelays not Investigated by Network Rail74
MUDepot operating problem73
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver17,284
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.11,380
M8Technical failures above the Solebar5,608
TITraincrew rostering problem5,575
I1Overhead line/third rail defect4,032
ICTrack circuit failure (including no fault found)3,673
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure3,612
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)3,234
IBPoints failure (including no fault found)3,179
IRBroken/cracked/twisted/buckled/flawed rail2,861