Shotts
439 delay minutes
The biggest share (17%) of the delay picked up at Shotts in the four weeks to 9 December 2023 came from autumn leaves.
73% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 8 | 2% | 8% | 0 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 23 | 5% | 16% | 1 a day, the least in 5 years | - |
| Weather and structures | 54 | 12% | 7% | 2 a day, more than 3 of the other 4 years | - |
| Autumn | 74 | 17% | 7% | 3 a day, the most in 5 years | - |
| External | 33 | 8% | 4% | 1 a day, the most in 5 years | - |
| Network management | 61 | 14% | 17% | 2 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 56 | 13% | 16% | 2 a day, more than 2 of the other 4 years | - |
| Traincrew | 40 | 9% | 11% | 1 a day, the least in 5 years | - |
| Stations | 15 | 3% | 3% | 1 a day, the least in 5 years | - |
| Operations | 14 | 3% | 5% | 1 a day, more than 1 of the other 4 years | - |
| Operator, other | 62 | 14% | 7% | 2 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 53 |
| TT | Leaf fall Neutral | 45 |
| XE | GSM-R call raised outside Network Rail network (by a non-track access party and/or for a legitimate safety issue) | 33 |
| JK | Flooding not due to exceptional weather | 29 |
| TH | (Senior) Conductor/Train Manager | 24 |
| QJ | Special working for leaf-fall track circuit operation | 18 |
| J8 | OTM DAMAGE | 16 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 16 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 16 |
| TG | Driver | 16 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 2,438 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 1,874 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 912 |
| IC | Track circuit failure (including no fault found) | 829 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 771 |
| MD | Technical failures below the solebar | 745 |
| Q3 | NZ Pumps T | 703 |
| M8 | Technical failures above the Solebar | 653 |
| IB | Points failure (including no fault found) | 585 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 575 |