Leaves on the Line

Shettleston

SLS Scotland route
CSV JSON

191 delay minutes

The biggest share (27%) of the delay picked up at Shettleston in the four weeks to 9 December 2023 came from other operator causes.

81% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track2212%8% 1 a day, more than 2 of the other 4 years-
Signals, points and power74%16% 0 a day, more than 1 of the other 4 years-
Weather and structures74%7% 0 a day, more than 2 of the other 4 years-
Autumn3619%7% 1 a day, more than 1 of the other 4 years-
External63%4% 0 a day, more than 2 of the other 4 years-
Network management179%17% 1 a day, the least in 5 years-
The operators' causes
Train faults158%16% 1 a day, the least in 5 years-
Traincrew2614%11% 1 a day, more than 3 of the other 4 years-
Stations42%3% 0 a day, the least in 5 years-
Operations--5% 0 a day, the least in 5 years-
Operator, other5227%7% 2 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Q3NZ Pumps T30
TGDriver26
MPRail / wheel interface, adhesion problems (including ice on the running rail)25
VHPassenger Communication cord, door egress or emergency train alarm operated12
ITRough ride or bumps reported - cause not known or no fault found11
VBVandalism or theft10
X9Points failure caused by severe snow or ice where heaters are fitted and working as designed7
M0Confirmed train cab based safety system fault (including GSMR)7
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.6
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)6
Since 2018
CodeWhat Network Rail loggedMinutes
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)1,041
TGDriver1,037
VHPassenger Communication cord, door egress or emergency train alarm operated793
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)716
M8Technical failures above the Solebar676
IBPoints failure (including no fault found)589
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure567
MPRail / wheel interface, adhesion problems (including ice on the running rail)560
JBReactionary Delay to 'P' coded TSRs556
Q3NZ Pumps T540