Leaves on the Line

St Neots

SNO East Coast route
CSV JSON

53 delay minutes

Most of the delay picked up at St Neots in the four weeks to 9 December 2023 came from how the network was run.

89% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management2955%17%1
The operators' causes
Train faults--16%1
Traincrew2445%11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver24
I5Possession over-run from planned work23
OCSignaller including mis-routing (not ERTM /ETCS related)3
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)3
Since 2018
CodeWhat Network Rail loggedMinutes
I1Overhead line/third rail defect408
X8Animal Strike or incursion not within the control of Network Rail73
TGDriver57
I9Fires starting on Network Rail Infrastructure41
TITraincrew rostering problem29
I5Possession over-run from planned work28
M8Technical failures above the Solebar27
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure27
MNBrake and brake systems faults; including wheel flats where no other cause had been identified26
XKNational Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed)18