Streatham Hill
517 delay minutes
Most of the delay picked up at Streatham Hill in the four weeks to 9 December 2023 came from track faults.
27% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 317 | 61% | 8% | 11 a day, the most in 5 years | - |
| Signals, points and power | 32 | 6% | 16% | 1 a day, more than 1 of the other 4 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | - | - | 7% | 0 a day, the least in 5 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 75 | 15% | 17% | 3 a day, more than 1 of the other 4 years | 21 |
| The operators' causes | |||||
| Train faults | 44 | 9% | 16% | 2 a day, more than 2 of the other 4 years | 3 |
| Traincrew | 9 | 2% | 11% | 0 a day, the least in 5 years | 1 |
| Stations | 3 | <1% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | 8 | 2% | 5% | 0 a day, more than 2 of the other 4 years | 1 |
| Operator, other | 29 | 6% | 7% | 1 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 317 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 28 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 25 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 14 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 13 |
| OB | Delayed by signaller not applying applicable regulating policy | 12 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 10 |
| M8 | Technical failures above the Solebar | 9 |
| MD | Technical failures below the solebar | 9 |
| TG | Driver | 9 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 3,904 |
| TG | Driver | 2,726 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,234 |
| OB | Delayed by signaller not applying applicable regulating policy | 1,329 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 1,208 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,162 |
| IC | Track circuit failure (including no fault found) | 735 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 615 |
| M8 | Technical failures above the Solebar | 482 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 464 |