Streatham
698 delay minutes
The biggest share (45%) of the delay picked up at Streatham in the four weeks to 9 December 2023 came from how the network was run.
63% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 22 | 3% | 8% | 1 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 133 | 19% | 16% | 5 a day, more than 1 of the other 4 years | 2 |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 5 | <1% | 7% | 0 a day, the least in 5 years | - |
| External | 7 | 1% | 4% | 0 a day, more than 1 of the other 4 years | - |
| Network management | 312 | 45% | 17% | 11 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 58 | 8% | 16% | 2 a day, more than 2 of the other 4 years | 1 |
| Traincrew | 88 | 13% | 11% | 3 a day, more than 1 of the other 4 years | - |
| Stations | 15 | 2% | 3% | 1 a day, more than 1 of the other 4 years | - |
| Operations | - | - | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 59 | 8% | 7% | 2 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 89 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 77 |
| TG | Driver | 74 |
| J3 | Axle Counter Failure | 49 |
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 45 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 44 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 32 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 29 |
| OB | Delayed by signaller not applying applicable regulating policy | 24 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 22 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 5,696 |
| TG | Driver | 4,353 |
| II | Signalling lineside cable fault | 3,061 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 2,800 |
| OB | Delayed by signaller not applying applicable regulating policy | 1,917 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 1,756 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,376 |
| M8 | Technical failures above the Solebar | 1,170 |
| IC | Track circuit failure (including no fault found) | 943 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 933 |