Leaves on the Line

Stirling

STG Scotland route
CSV JSON

1,433 delay minutes

The biggest share (19%) of the delay picked up at Stirling in the four weeks to 9 December 2023 came from track faults.

64% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track26819%8% 10 a day, the most in 5 years-
Signals, points and power14110%16% 5 a day, more than 1 of the other 4 years-
Weather and structures23216%7% 8 a day, more than 3 of the other 4 years3
Autumn715%7% 3 a day, more than 2 of the other 4 years-
External14<1%4% 1 a day, the least in 5 years1
Network management1339%17% 5 a day, more than 1 of the other 4 years18
The operators' causes
Train faults22115%16% 8 a day, more than 2 of the other 4 years5
Traincrew594%11% 2 a day, more than 1 of the other 4 years1
Stations675%3% 2 a day, more than 3 of the other 4 years-
Operations1067%5% 4 a day, the most in 5 years-
Operator, other1229%7% 4 a day, more than 2 of the other 4 years5

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.248
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions139
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)85
MPRail / wheel interface, adhesion problems (including ice on the running rail)76
Q3NZ Pumps T68
M0Confirmed train cab based safety system fault (including GSMR)61
MDTechnical failures below the solebar51
M8Technical failures above the Solebar46
X9Points failure caused by severe snow or ice where heaters are fitted and working as designed45
JKFlooding not due to exceptional weather42
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver5,298
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions5,019
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)4,204
ZUNo Cause Identified After investigation by both Parties2,671
MDTechnical failures below the solebar2,558
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure2,371
M8Technical failures above the Solebar2,327
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure2,296
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,102
OCSignaller including mis-routing (not ERTM /ETCS related)1,698