Stirling
1,433 delay minutes
The biggest share (19%) of the delay picked up at Stirling in the four weeks to 9 December 2023 came from track faults.
64% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 268 | 19% | 8% | 10 a day, the most in 5 years | - |
| Signals, points and power | 141 | 10% | 16% | 5 a day, more than 1 of the other 4 years | - |
| Weather and structures | 232 | 16% | 7% | 8 a day, more than 3 of the other 4 years | 3 |
| Autumn | 71 | 5% | 7% | 3 a day, more than 2 of the other 4 years | - |
| External | 14 | <1% | 4% | 1 a day, the least in 5 years | 1 |
| Network management | 133 | 9% | 17% | 5 a day, more than 1 of the other 4 years | 18 |
| The operators' causes | |||||
| Train faults | 221 | 15% | 16% | 8 a day, more than 2 of the other 4 years | 5 |
| Traincrew | 59 | 4% | 11% | 2 a day, more than 1 of the other 4 years | 1 |
| Stations | 67 | 5% | 3% | 2 a day, more than 3 of the other 4 years | - |
| Operations | 106 | 7% | 5% | 4 a day, the most in 5 years | - |
| Operator, other | 122 | 9% | 7% | 4 a day, more than 2 of the other 4 years | 5 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 248 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 139 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 85 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 76 |
| Q3 | NZ Pumps T | 68 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 61 |
| MD | Technical failures below the solebar | 51 |
| M8 | Technical failures above the Solebar | 46 |
| X9 | Points failure caused by severe snow or ice where heaters are fitted and working as designed | 45 |
| JK | Flooding not due to exceptional weather | 42 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 5,298 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 5,019 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 4,204 |
| ZU | No Cause Identified After investigation by both Parties | 2,671 |
| MD | Technical failures below the solebar | 2,558 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,371 |
| M8 | Technical failures above the Solebar | 2,327 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 2,296 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,102 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,698 |