Leaves on the Line

Severn Tunnel Junction

STJ Wales route
CSV JSON

281 delay minutes

The biggest share (21%) of the delay picked up at Severn Tunnel Junction in the four weeks to 9 December 2023 came from faulty trains.

63% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track41%8% 0 a day, more than 3 of the other 4 years-
Signals, points and power269%16% 1 a day, more than 1 of the other 4 years-
Weather and structures62%7% 0 a day, more than 3 of the other 4 years-
Autumn--7% 0 a day, the least in 5 years-
External4416%4% 2 a day, the most in 5 years-
Network management5219%17% 2 a day, more than 2 of the other 4 years2
The operators' causes
Train faults5821%16% 2 a day, more than 2 of the other 4 years1
Traincrew3713%11% 1 a day, the most in 5 years-
Stations145%3% 1 a day, the most in 5 years-
Operations2810%5% 1 a day, the most in 5 years-
Operator, other124%7% 0 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
XPBRIDGE HIT32
MDTechnical failures below the solebar25
ICTrack circuit failure (including no fault found)16
I5Possession over-run from planned work13
M7Door and Door system faults12
FHFOC Planning issue (not diagramming or rostering)11
TGDriver11
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps10
ACWaiting Train preparation or completion of TOPS list/RT39739
TH(Senior) Conductor/Train Manager9
Since 2018
CodeWhat Network Rail loggedMinutes
JSCondition of Track TSR outside the Timetable Planning Rules10,723
IBPoints failure (including no fault found)1,741
I1Overhead line/third rail defect1,451
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure1,442
OTOps Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused)1,285
IRBroken/cracked/twisted/buckled/flawed rail1,282
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,277
J3Axle Counter Failure1,175
MDTechnical failures below the solebar1,099
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)1,060