Severn Tunnel Junction
281 delay minutes
The biggest share (21%) of the delay picked up at Severn Tunnel Junction in the four weeks to 9 December 2023 came from faulty trains.
63% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 4 | 1% | 8% | 0 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 26 | 9% | 16% | 1 a day, more than 1 of the other 4 years | - |
| Weather and structures | 6 | 2% | 7% | 0 a day, more than 3 of the other 4 years | - |
| Autumn | - | - | 7% | 0 a day, the least in 5 years | - |
| External | 44 | 16% | 4% | 2 a day, the most in 5 years | - |
| Network management | 52 | 19% | 17% | 2 a day, more than 2 of the other 4 years | 2 |
| The operators' causes | |||||
| Train faults | 58 | 21% | 16% | 2 a day, more than 2 of the other 4 years | 1 |
| Traincrew | 37 | 13% | 11% | 1 a day, the most in 5 years | - |
| Stations | 14 | 5% | 3% | 1 a day, the most in 5 years | - |
| Operations | 28 | 10% | 5% | 1 a day, the most in 5 years | - |
| Operator, other | 12 | 4% | 7% | 0 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| XP | BRIDGE HIT | 32 |
| MD | Technical failures below the solebar | 25 |
| IC | Track circuit failure (including no fault found) | 16 |
| I5 | Possession over-run from planned work | 13 |
| M7 | Door and Door system faults | 12 |
| FH | FOC Planning issue (not diagramming or rostering) | 11 |
| TG | Driver | 11 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 10 |
| AC | Waiting Train preparation or completion of TOPS list/RT3973 | 9 |
| TH | (Senior) Conductor/Train Manager | 9 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JS | Condition of Track TSR outside the Timetable Planning Rules | 10,723 |
| IB | Points failure (including no fault found) | 1,741 |
| I1 | Overhead line/third rail defect | 1,451 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 1,442 |
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 1,285 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 1,282 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,277 |
| J3 | Axle Counter Failure | 1,175 |
| MD | Technical failures below the solebar | 1,099 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 1,060 |