Leaves on the Line

Stonehaven

STN Scotland route
CSV JSON

534 delay minutes

Most of the delay picked up at Stonehaven in the four weeks to 9 December 2023 came from weather and structures.

37% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track224%8% 1 a day, more than 2 of the other 4 years-
Signals, points and power285%16% 1 a day, more than 2 of the other 4 years1
Weather and structures33463%7% 12 a day, the most in 5 years-
Autumn61%7% 0 a day, more than 1 of the other 4 years-
External4<1%4% 0 a day, more than 1 of the other 4 years-
Network management5911%17% 2 a day, more than 3 of the other 4 years5
The operators' causes
Train faults357%16% 1 a day, more than 2 of the other 4 years-
Traincrew295%11% 1 a day, more than 3 of the other 4 years-
Stations2<1%3% 0 a day, the least in 5 years-
Operations92%5% 0 a day, more than 3 of the other 4 years-
Operator, other61%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions287
X9Points failure caused by severe snow or ice where heaters are fitted and working as designed36
ZUNo Cause Identified After investigation by both Parties29
TGDriver26
IRBroken/cracked/twisted/buckled/flawed rail22
M8Technical failures above the Solebar16
MDTechnical failures below the solebar16
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure12
I5Possession over-run from planned work9
IKTelecom equipment failure (including no fault found)9
Since 2018
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions2,159
ZUNo Cause Identified After investigation by both Parties1,848
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,730
MDTechnical failures below the solebar1,214
M8Technical failures above the Solebar1,167
TGDriver1,151
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure860
IBPoints failure (including no fault found)766
IASignal failure (including no fault found)590
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)585