Sutton (London)
2,325 delay minutes
The biggest share (32%) of the delay picked up at Sutton (London) in the four weeks to 9 December 2023 came from how the network was run.
81% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 43 | 2% | 8% | 2 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 638 | 27% | 16% | 23 a day, the most in 5 years | 12 |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 51 | 2% | 7% | 2 a day, more than 2 of the other 4 years | - |
| External | 15 | <1% | 4% | 1 a day, the least in 5 years | 9 |
| Network management | 733 | 32% | 17% | 26 a day, more than 2 of the other 4 years | 35 |
| The operators' causes | |||||
| Train faults | 155 | 7% | 16% | 6 a day, the least in 5 years | 4 |
| Traincrew | 375 | 16% | 11% | 13 a day, more than 2 of the other 4 years | 11 |
| Stations | 63 | 3% | 3% | 2 a day, more than 2 of the other 4 years | - |
| Operations | - | - | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 252 | 11% | 7% | 9 a day, more than 2 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 300 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 242 |
| J3 | Axle Counter Failure | 208 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 195 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 144 |
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 133 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 89 |
| J0 | Telecom equipment radio failure (GSM-R) | 62 |
| I1 | Overhead line/third rail defect | 60 |
| IC | Track circuit failure (including no fault found) | 59 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 19,900 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 12,670 |
| M8 | Technical failures above the Solebar | 7,735 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 6,474 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 6,263 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 4,904 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 4,696 |
| IC | Track circuit failure (including no fault found) | 4,620 |
| IB | Points failure (including no fault found) | 3,966 |
| OB | Delayed by signaller not applying applicable regulating policy | 3,755 |