33 delay minutes

The biggest share (36%) of the delay picked up at Wick in the four weeks to 9 December 2023 came from weather and structures.

42% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures1236%7%-
Autumn--7%-
External--4%-
Network management1236%17%-
The operators' causes
Train faults927%16%3
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
I8Animal Strike or Incursion within the control of Network Rail9
MDTechnical failures below the solebar9
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions7
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)5
ZUNo Cause Identified After investigation by both Parties3
Since 2018
CodeWhat Network Rail loggedMinutes
IRBroken/cracked/twisted/buckled/flawed rail759
MDTechnical failures below the solebar345
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions180
XKNational Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed)126
TGDriver122
M8Technical failures above the Solebar114
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure109
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)96
ZUNo Cause Identified After investigation by both Parties92
I0Telecom equipment legacy radio failures (RETB)89