Leaves on the Line

West Calder

WCL Scotland route
CSV JSON

10 delay minutes

Most of the delay picked up at West Calder in the four weeks to 9 December 2023 came from outside causes like vandalism, cable theft, animals and fires.

70% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn215%7%-
External770%4%1
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other215%7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
XEGSM-R call raised outside Network Rail network (by a non-track access party and/or for a legitimate safety issue)7
Q3NZ Pumps T2
TTLeaf fall Neutral2
Since 2018
CodeWhat Network Rail loggedMinutes
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure104
MCDiesel Loco failure, defect, attention51
XPBRIDGE HIT25
I2AC/DC trip (including no fault or cause found)15
IHPower Supply And Distribution System Failure14
TGDriver13
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)9
IRBroken/cracked/twisted/buckled/flawed rail8
XEGSM-R call raised outside Network Rail network (by a non-track access party and/or for a legitimate safety issue)7
IBPoints failure (including no fault found)6