Leaves on the Line

Westerton

WES Scotland route
CSV JSON

590 delay minutes

The biggest share (19%) of the delay picked up at Westerton in the four weeks to 9 December 2023 came from other operator causes.

72% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track5710%8% 2 a day, more than 3 of the other 4 years-
Signals, points and power295%16% 1 a day, more than 1 of the other 4 years3
Weather and structures458%7% 2 a day, the most in 5 years-
Autumn7212%7% 3 a day, the least in 5 years-
External244%4% 1 a day, more than 3 of the other 4 years-
Network management9616%17% 3 a day, more than 2 of the other 4 years1
The operators' causes
Train faults7613%16% 3 a day, more than 1 of the other 4 years1
Traincrew468%11% 2 a day, more than 2 of the other 4 years-
Stations81%3% 0 a day, more than 1 of the other 4 years-
Operations254%5% 1 a day, more than 2 of the other 4 years-
Operator, other11319%7% 4 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
JPFailure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards53
Q3NZ Pumps T53
MPRail / wheel interface, adhesion problems (including ice on the running rail)48
TGDriver38
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions37
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.35
VWSevere weather affecting passenger Fleet equipment including follwogin company standards/policies or Rule book instructions26
MNBrake and brake systems faults; including wheel flats where no other cause had been identified25
JBReactionary Delay to 'P' coded TSRs22
VHPassenger Communication cord, door egress or emergency train alarm operated19
Since 2018
CodeWhat Network Rail loggedMinutes
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)3,621
TGDriver2,894
M8Technical failures above the Solebar1,846
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)1,539
MPRail / wheel interface, adhesion problems (including ice on the running rail)1,352
Q3NZ Pumps T1,332
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure1,133
MDTechnical failures below the solebar1,080
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,013
M7Door and Door system faults1,012