Welshpool
737 delay minutes
The biggest share (23%) of the delay picked up at Welshpool in the four weeks to 9 December 2023 came from signal, points and power faults.
92% of these minutes were knock-on from something that happened elsewhere first. 83% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 166 | 23% | 16% | 6 a day, more than 3 of the other 4 years | - |
| Weather and structures | 26 | 4% | 7% | 1 a day, more than 2 of the other 4 years | - |
| Autumn | 112 | 15% | 7% | 4 a day, the most in 5 years | - |
| External | 15 | 2% | 4% | 1 a day, more than 2 of the other 4 years | - |
| Network management | 79 | 11% | 17% | 3 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 152 | 21% | 16% | 5 a day, more than 2 of the other 4 years | - |
| Traincrew | 107 | 15% | 11% | 4 a day, more than 3 of the other 4 years | - |
| Stations | 8 | 1% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | 40 | 5% | 5% | 1 a day, more than 3 of the other 4 years | 5 |
| Operator, other | 32 | 4% | 7% | 1 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 70 |
| QH | Adhesion problems due to leaf contamination | 58 |
| QI | Cautioning due to railhead leaf contamination | 54 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 51 |
| IC | Track circuit failure (including no fault found) | 37 |
| TZ | Other Passenger Train Operating Company causes | 36 |
| J0 | Telecom equipment radio failure (GSM-R) | 34 |
| TH | (Senior) Conductor/Train Manager | 34 |
| M8 | Technical failures above the Solebar | 31 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 26 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 1,629 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 1,556 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 1,353 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 1,312 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 1,292 |
| TG | Driver | 1,191 |
| J0 | Telecom equipment radio failure (GSM-R) | 1,185 |
| M8 | Technical failures above the Solebar | 1,087 |
| TZ | Other Passenger Train Operating Company causes | 1,025 |
| OU | Delays not Investigated by Network Rail | 1,013 |