Wemyss Bay
184 delay minutes
The biggest share (25%) of the delay picked up at Wemyss Bay in the four weeks to 9 December 2023 came from signal, points and power faults.
32% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 46 | 25% | 16% | 2 a day, more than 1 of the other 4 years | - |
| Weather and structures | 39 | 21% | 7% | 1 a day, the most in 5 years | 1 |
| Autumn | 24 | 13% | 7% | 1 a day, more than 3 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 17 | 9% | 17% | 1 a day, more than 2 of the other 4 years | 1 |
| The operators' causes | |||||
| Train faults | 17 | 9% | 16% | 1 a day, more than 2 of the other 4 years | 1 |
| Traincrew | 8 | 4% | 11% | 0 a day, the most in 5 years | 1 |
| Stations | 3 | 2% | 3% | 0 a day, more than 2 of the other 4 years | - |
| Operations | 10 | 5% | 5% | 0 a day, more than 3 of the other 4 years | 1 |
| Operator, other | 21 | 11% | 7% | 1 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IA | Signal failure (including no fault found) | 43 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 25 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 21 |
| Q3 | NZ Pumps T | 21 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 14 |
| X9 | Points failure caused by severe snow or ice where heaters are fitted and working as designed | 14 |
| TA | Train-crew/loco/stock/unit diagram issues | 10 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 9 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 8 |
| TG | Driver | 8 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 1,326 |
| TG | Driver | 437 |
| IB | Points failure (including no fault found) | 399 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 270 |
| Q3 | NZ Pumps T | 252 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 244 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 228 |
| IC | Track circuit failure (including no fault found) | 227 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 217 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 213 |