Leaves on the Line

Yoker

YOK Scotland route
CSV JSON

8 delay minutes

Most of the delay picked up at Yoker in the four weeks to 9 December 2023 came from how the network was run.

63% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management8100%17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%1
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)8
Since 2018
CodeWhat Network Rail loggedMinutes
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure76
M8Technical failures above the Solebar55
MNBrake and brake systems faults; including wheel flats where no other cause had been identified53
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure33
IBPoints failure (including no fault found)26
XTSevere snow or ice affecting infrastructure which is the responsibility of NR (including implementation of Key Route Strategy)26
TGDriver23
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.16
TZOther Passenger Train Operating Company causes16
QICautioning due to railhead leaf contamination15